Reference | MOC/25/04/00037 | Customer | Joe Kavlie |
---|---|---|---|
Date | 04/09/2025 | Build Date | Not Confirmed. |
Material Colors
Material Order(s)
There are no material order.
Initial Numbers vs Final Numbers
Initial Insurance Pricing: $ 6,394.64
Initial | ||||
---|---|---|---|---|
Labor Estimate | Materials Estimate | Estimated Project Costs | Profit Estimate | Margin (%) |
$ 6,940.00 | $ 5,284.97 | $ 12,224.97 | $ -5,830.33 | -47.7 % |
Initial Homeowner Compensation Estimate: $ -2,915.17
Initial Consulting Fee Estimate : $ -2,915.17
Consulting Down Payment (1/2 of Initial Consulting Fee Estimate): $ -1,457.59
Estimated Project Costs : $ 12,224.97
Labor Costs: $ 6,940.00
Material Costs: $ 5,284.97
Total Insurance : $ 6,394.64
Project Costs: $ 12,224.97
Total Profit: $ -5,830.33
Final Insurance Pricing: $ 0.00
Final Labor | Final Materials | Final Project Costs | Final Profit | Final Margin (%) |
---|---|---|---|---|
$ 0.00 | $ 0.00 | $ 0.00 | $ 0.00 | 0% |
Final Homeowner Compensation: $ 0.00
Final Consulting Fee: $ 0.00
Final Consulting Payment: $ 1,457.59
Final Project Costs : $ 0.00
Labor Costs: $ 0.00
Material Costs: $ 0.00
Total Insurance : $ 0.00
Project Costs: $ 0.00
Total Profit: $ 0.00