General Information

Reference MOC/25/04/00037 Customer Joe Kavlie
Date 04/09/2025 Build Date Not Confirmed.

Material Colors

Material Order(s)

There are no material order.

Initial Numbers vs Final Numbers

Initial Insurance Pricing: 6,394.64

Initial
Labor Estimate Materials Estimate Estimated Project Costs Profit Estimate Margin (%)
6,940.00 5,284.97 12,224.97 -5,830.33 -47.7 %
Initial Homeowner Compensation Estimate: -2,915.17
Initial Consulting Fee Estimate : -2,915.17
Consulting Down Payment (1/2 of Initial Consulting Fee Estimate): -1,457.59

Estimated Project Costs : 12,224.97

Labor Costs: 6,940.00
Material Costs: 5,284.97

Total Insurance : 6,394.64

Project Costs: 12,224.97
Total Profit: -5,830.33

Final Insurance Pricing: 0.00

Final Labor Final Materials Final Project Costs Final Profit Final Margin (%)
0.00 0.00 0.00 0.00 0%
Final Homeowner Compensation: 0.00
Final Consulting Fee: 0.00
Final Consulting Payment: 1,457.59

Final Project Costs : 0.00

Labor Costs: 0.00
Material Costs: 0.00

Total Insurance : 0.00

Project Costs: 0.00
Total Profit: 0.00