Reference MOC/25/09/00051 Customer JH - Elk River
Date 08/27/2025 Material Order Status Not Ordered

Material Colors

Timberline HDZ (Mission Brown)

Initial Numbers vs Final Numbers

Initial Insurance Pricing: 24,500.00

Initial
Labor Estimate Materials Estimate Estimated Project Costs Profit Estimate Margin (%)
7,250.00 6,910.46 14,160.46 10,339.54 42.2 %
Initial Homeowner Compensation Estimate: 5,169.77
1/2 Profit Estimate: 5,169.77
Initial Consulting Fee Estimate : 5,169.77
Consulting Down Payment (1/2 of Initial Consulting Fee Estimate): 2,584.89

Estimated Project Costs : 14,160.46

Labor Costs: 7,250.00
Material Costs: 6,910.46

Total Insurance : 24,500.00

Project Costs: 14,160.46
Total Profit: 10,339.54

Final Insurance Pricing: 0.00

Final Labor Final Materials Final Project Costs Final Profit Final Margin (%)
0.00 0.00 0.00 0.00 0%
Final Homeowner Compensation: 0.00
Final Consulting Fee: 0.00
Final Consulting Payment: -2,584.89

Final Project Costs : 0.00

Labor Costs: 0.00
Material Costs: 0.00

Total Insurance : 0.00

Project Costs: 0.00
Total Profit: 0.00